TCW00078 Kulburn Booster Pump Station

Project Description / Overview:

The aim of this project is to construct a new booster pump station to pump water to Kulburn reservoir and northern areas of Townsville. The works involves a Pump House building construction to house new pumps, associated pipework connections to mains and tie-in works. Along with connection of electrical and instrumentation for the pumps and commissioning of the installed system.

Client:

TCC

Project Features:

  • Earthworks Construction of building pad
  • Pump House Building Construction
  • Pipe work and cut-in to mains installations
  • Supply and installation of Pumps & standby generator
  • Electrical & Instrumentation Installation
  • Commissioning of the works.