Ravenswood Sediment Dam

Project Description / Overview:

Carpentaria Gold have engaged C+ Services to construct a sediment dam on the Ravenswood Mine Site. The purpose of the works is to capture runoff from the adjacent waste rock dumps prior to runoff entering Sandy Creek Downstream.

Client:

Carpentaria Gold

Project Features:


Scope of these works include:
*Avoiding cultural heritage and environmentally sensitive areas.
*Excavation of Dirty Water Drains including removal and spoiling of unsuitable or excess material.
*Excavation of spillway channel and spillway road crossing/access ramp including removal and spoiling of unsuitable or excess material.
*Supply & install of erosion protection works including rock lined channels and spillway erosion protection.
*Construction of new spillway from the dam including a concrete sil.
*Sourcing suitable fill materials which conform to the requirements of the specification.
*Hydro mulch and topsoiling the works to establish vegetation cover.