Caltibiano Subdivision

Project Description / Overview:

Completion of:

8 Lot sub division including sealed access roads, water reticulation, sewer reticulation, stormwater pipes, bulk earthworks and drainage works. Worked with client to overcome problems which a rose with clashes of alignment of services. All works completed on program and budget with delivery of project through the Wet Season.

Client:

D&D Luck Family Trust

Project Features:


    Bulk earthworks on site cut to fill.
  • Installation of water main, inc hose connections and hydrants
  • Installation of Sewer Mains
  • Installation of Stormwater pipe and Pits.
  • Laying of kerb for access roads
  • Place gravel and bitumen seal for access roads
  • Project completed ahead of program and on budget
  • No major variations claimed