CSR Permanent Bridge Repairs Lander Creek & Expedition Pass

Project Description / Overview:

This Contract was located at Landers Creek & Expedition Pass near Clare on the Ayr/Dalbeg Rd. During recent flooding events both bridges sustained significant damage through displacement of the bridge girder beams and snapping the pier supports off at the foundation piles. The project included installation of new piles, installation of pile caps, piers & headstocks, steel repairs to internal and external beams.

Client:

CSR

Project Features:

  • Traffic Management
  • Two different locations over 20km
  • Logistics
  • Structural steel fabrication
  • Bearing pad replacement
  • Location of existing piles in river bed
  • Bored pile construction
  • Concrete head stock and piers