Birthday Creek Bridge Replacement

Project Description / Overview:

The works involve demolition and removal off-site of the existing bridge super- structure and foundations. Design and documentation of a new precast concrete bridge superstructure including precast deck, abutment headstocks, wing-walls and precast facing panel to the abutments, including all attachments and fixings. Construction of bridge foundations, installation of pre-cast concrete abutment headstocks and concrete deck members, regrading of approaches and construction of abutment protection works.

Client:

Townsville City Council

Project Features:

  • Abutment Headstock
  • Cast Insitu Board Piers
  • Wing-walls
  • Rock Protection
  • Road Approaches
  • Humedeck System
  • Cranage of Bridge Decks
  • Derm Permits
  • Excess Mass Permits
  • Platypus Management