500m of Detour for Gregory Developmental Road around the edge of the Highway Reward Pit approximately 30km South of Charters Towers. Due to circumstances that had developed on site prior to our mobilisation, the project had to be completed immediately to satisfy the requirements of Main Roads. By sourcing local resources which we had a working relationship for importing of Subbase
as a variation to the contract we were able to complete all works 4 days ahead of schedule.