QN Port Stack Footing

  • Name:
    QN Port Stack Footing
  • Client:
    Queensland Nickel
  • Related Service/s:

Project Overview / Description

Installation of reinforced concrete footing to support the oil furnace stack, the footing was supported by driven precast piles. The works including two small stormwater pits, nib walls and small amount of piping to ensure that all stormwater was captured and diverted to the oil water separator. A Lighting protection
system was also installed in the foundation for future connection to the stack if required.

Project Features:

    • Removal of existing concrete slabs
    • Installation of 6 precast driven piles to a depth of approx. 23m
    • Vibration monitoring during pile installation for integrity of surrounding structures
    • Trimming of piles Installation of Lighting Protection System
    • Installation of 40m3 of Reinforced Concrete
    • Two small storm water pits
    • Backfilling around footing and leaving site tidy
    • Project completed on time and budget