Waterway Gardens Trunk Main

Project Overview / Description

Installation of 200m of DN600 DICL fully flanged pipe with associated thrust blocks and 150m of DN200 RRJ pipe. The DN600mm main included a component of Tunnel Boring installation of an enveloper and then installing the pipe into the enveloper.

Due to issues encountered on the project a detour of the Bruce Highway had to be constructed in short time to allow works to continue for the trunk main installation. Works also included a tunnel bore underneath the Main Northern QR line at a depth of approximately 3m.

Project Features:

    • Installation of 200m of DN600 fully flanged DICL pipe
    • Installation of 65m of 960mm Enveloper pipe
    • Installation of MSCL pipe specials
    • Installation of 150m of DN200 RRJ pipe
    • Installation of thrust blocks
    • Installation of 450RCP Envelopers for road crossing
    • Installation of detour for 24,800 vehicle per day road and associated traffic control
    • Project completed on time with no LTI’s