Highway Reward Minesite - Highway Detour

Project Overview / Description

500m of Detour for Gregory Developmental Road around the edge of the Highway Reward Pit approximately 30km South of Charters Towers. Due to circumstances that had developed on site prior to our mobilisation, the project had to be completed immediately to satisfy the requirements of Main Roads. By sourcing local resources which we had a working relationship for importing of Subbase
as a variation to the contract we were able to complete all works 4 days ahead of schedule.

Project Features:

    • Bulk earthworks on site for subgarde
    • Win material from mine site and cart to the detour
    • Placement, compaction and trimming of 500m of pavement materials
    • Tie ins at either end of detour to the Gregory Developmental Road
    • All works completed to the satisfaction of the Main Roads Inspector