The TPIX Inner Harbour Project requires CivilPlus Constructions to install the utilities services to wharf 10A as part of the harbour expansion. The services include Fire, Potable Water, Diesel and...
The Townsville Recreational Boating Park TRBP) will consist of four boat ramps each with four lanes and centre floating walkway. The project will also include an adequate number of car trailer...
Additional On Shore Works for Townsville City Council:
South Townsville Stormwater Drainage
43m of 18x12 Precast culverts and bases
Manhole to suit 18x12 culverts
Outlet structure to suit...
CivilPlus were engaged by Serco Sodexo to complete remediation works on the Australian Defence Force Tully Training Area Access Roads. These works included construction of a 50mtr retaining wall,...
Design and install a feed mill to process 350tonne of livestock feed per week. This consisted of assisting with concept design, approving layouts and then managing the designers though to...
Completion of various pavement repairs and hardstands at MSTA, Many Peaks, Runway Investigation and Lavarack Parade Grounds. Works included removal and replace of pavement, installation of new...
CivilPlus were engaged by Serco Sodexo to complete remediation works at the high range training facility. These works included excavation of existing road and subgrade, placement of geo grid and...
Installation of Valve pit, flow metering slab and interconnecting pipework. The valve pit consisted of a 5m x 3m x 3m deep valve pit for the connection to the underground DN600m main which was...
Installation of 200m of DN600 DICL fully flanged pipe with associated thrust blocks and 150m of DN200 RRJ pipe. The DN600mm main included a component of Tunnel Boring installation of an enveloper...
Installation of new 800mm MSCL pipe line to allow for the new highway intersection to be installed. The works included large inground valve pits at each end of the line, large inground thrust...
Project Works included the removal of the existing DN200 water line which ran from the floating pump station in the dam to the treatment plant on the bank, which was a total distance of 550m. Once...