All Projects

Mainteck Ring Beams

Client: Mainteck

Civil & Concrete Works for conveyor drive station.
Cape Hotham projects into the Van Dieman Gulf, approximately 80 km (direct line) NE of Darwin. The structure is a steel lattice tower capped by the lantern room with a copper roof. Surfaces to be...

McDowells Pipeline Construction

Client: North Burdekin Water Board

Construct 1.2km of DN1300 pipeline to replace the existing redundant pipeline along Mann Road, Home Hill. 1.2km of DN1300 GRP Pipeline 29m of microtunneling under kirknie Road and Tram Line...

Mornington Island Jetty Demolition

Client: Mornington Shire Council

Removal and Replacement of Piles on Jetty
The aim of this project was to carry out civil repair to the deteriorated sealed munitions compound pavement at Mt Stuart Training Area to enable better access to training facilities in order to...
CivilPlus were engaged by Serco Sedexo for the refurbishment of the Range Target Mounds at MSTA. The works included placing bitum on re-compacted scour, placement of geoweb with fibre glass pins...

Mt Isa ARES Depot Civil Works

Client: Department of Defence

NQ1648 MIRR/3122 The Upgrade of the Mt Isa ARES depot pavement and hardstand areas. This included upgrading of the parade and parking bays for the depot, along with concrete light vehicle hardstand.

Mt Louisa Pipeline

Client: JJ McDonald & Sons Engineering Pty Ltd

Pipe Welding Subcontract CivilPlus (previously CivMEC) Constructions were initially subcontracted to complete the internal and external welds of the 800mm diameter MSCL Pipeline. However our scope...

Mt Low Parkway Subdivision

Client: D&D Luck Family Trust

Completion of 14 Lot sub division including sealed access roads, water reticulation, bulk earthworks and drainage works. Worked with client to overcome problems which arose with clashes of...

Mt Stuart Road Bridge Rehabilitation

Client: Townsville City Council

CivilPlus was awarded the project from Townsville City Council for the rehabilitation of the vehicle and pedestrian bridge on Mount Stuart Road. The bridge is situated at the intersection of Mount...
The aim of this project is for maintainance on the Infrustructure at the defence training facility, in particular the roadway to the MTR upgraded a gravel road to a Bitumen sealed road. This...

Nelly Bay Road Pathway

Client: Townsville City Council

CivilPlus completed the concrete pathway from Base Backpackers Resort to Yates Street for the Townsville City Council to improve access for island users. This project required community and...
The aim of this project is to provide temporary new facilities to house the relocation of two close health companies. CivilPlus is completing the pre-works and services that includes drainage, bulk...
This Contract was located at Ollera Creek near the foot of the Paluma Range. The objective was to remediate the existing pipeline surface where rusting had occurred due to river debris impacting...

Orpheus Island Jetty Construction

Client: Orpheus Island

The aim of this project is to replace the damaged existing jetty with a new Steel Substructure with timber decking jetty on Orpheus Island. This included driven steel pile with steel headstocks and...
Project Description / Overview:Installation of removal and replacement of sections of pipes ranging in size from 445mm to 660mm in areas with extremely difficult access and in the World Tropics...

Paluma Dam Concrete Remediation

Client: Townsville City Council

The concrete dam inlet tower and outlet pipe has become dilapidated over time requiring remediation to stop current corrosion and further deterioration and water ingress.

Pedestrian Bridge

Client: Seymour White

Ring Road Pedestrian Underpass Extension Works

Phosphate Roadworks

Client: Incitec Pivot Limited

Carry out Road Repairs at Phosphate Mine Site

Picnic Bay Landfill

Client: Townsville City Council

CivilPlus has just completed works at the Picnic Bay Landfill. This project required the capping of the closed solid waste landfill at the Picnic Bay site. The purpose of these works was to create...

POTL Road Repairs

Client: Port of Townsville

Road Repairs

POTL Stormwater Drainage

Client: Port of Townsville

POTL required a new RCBC (2.4 x 1.5mtrs) drainage system to reduce flood zones and to allow future expansion sites to be available & suitable for construction as approved.

Pre Cast Planks

Client: Pacific Marine Group

Constructions of Pre Cast Concrete Planks for Abbott Point Barge Landing Facility

Proserpine Boat Ramp

Client: Department of Transport & Main Roads

The Proserpine Boat ramp required upgrading to provide safer and increased access by the community. The major items included in the Works are: Design of the floating walkway (including construction...
Installation of Civil Works for Palm Island Jetty & Barge Ramp Upgrade, which included placement of select fill, placement of armour rock, Precast & Cast insitu items for the Barge ramp...

QN Fuel Oil Line Repairs

Client: Queensland Nickel

Installation of repairs to QN fuel oil line at approximately 37 locations between the Port of Townsville and QN Yabulu Refinery. This scope of works included the excavation of the sections of pipe,...

QN Plinth Remediation

Client: Queensland Nickel

Existing concrete bases has dilapidated and required concrete repairs to ensure structural integrity.

QN Port Stack Footing

Client: Queensland Nickel

Installation of reinforced concrete footing to support the oil furnace stack, the footing was supported by driven precast piles. The works including two small stormwater pits, nib walls and small...

QN Road Works

Client: Queensland Nickel

Project Description / Overview:CivilPlus are currently contracted by Queensland Nickel to reconstruct the main intersection at the Yabulu refinery due to a failing pavement causing continuous...

QN Thickner Base Construction

Client: BHP Billiton Yabulu Refinery

Civil rectification of Thickener floor and concrete sub-structure, including changing the floor configuration to suit new thickener design.

QN Ware House Project

Client: Queensland Nickel

Civilplus have been contracted to install 240m of 1500 span concrete inverted culvert to the perimeter of the main warehouse facility at Queensland Nickel. This is to provide drainage to the...

QN WCS Concrete Works

Client: Queensland Nickel

The works consist of removal of existing guard rail and concrete slab, location of existing HV services, preparation of foundations and construction of 3 pad footings to accommodate two new plate...

QR Brandon Culvert Constructions

Client: Queensland Rail

Existing rail track drainage system had failed under the road causing subsidence and cracking in the road surface and the potential for road failure if not repaired in due course.
CivilPlus was engaged to completely remove the AC effluent pipe and supporting structure for subsequent demolition and disposal.
CivilPlus were engaged by Serco Sodexo to design and construct a concrete car park at the Townsville RAAF Base for Air Services Australia. These works included geofabric placement over uneven...
Demolition at three fuel hydrant locations, Concrete slab (nil reinforcing) 1.5m wide x 10m long x 0.4 - 0.5m deep, Including concrete at hydrant and high point surrounds, Low point drains...

RAAF Retention Pond

Client: Spotless

CivilPlus were engaged to construct a 180,000L Spelceptor tank at the RAAF Base fuel farm, this included precast items for the fire trap and anchor blocks. The 4m deep excavation was sheet piled to...

RAAF Road Repairs

Client: SSDS / DEFENCE

This Contract was located on the Townsville RAAF Base between Hangar 75 & the quadron 38 area. The pavement required repairs and the project involved the design & re-construction of the...

Ravenswood Sediment Dam

Client: Carpentaria Gold

Carpentaria Gold have engaged C+ Services to construct a sediment dam on the Ravenswood Mine Site. The purpose of the works is to capture runoff from the adjacent waste rock dumps prior to runoff...

Richmond Road Repairs

Client: Richmond Shire Council

Civilplus worked in conjunction with the Richmond Shire Council to complete Flood damage repairs on the Department of Main Roads owned Flinders Highway. This works consisted of catergorising...

Riverside Pedestrian Bridge

Client: Townsville City Council

The works consisted of demolishing and removal of existing bridge and abutments, and fabrication and installation of a steel painted bridge with connecting concrete pathways as per A.S and council...

Riverway Drive Gabion Structure

Client: Townsville City Council

Due to severe scouring of the river bank, Townsville City Council contracted CivilPlus to complete a designed gabion structure to restore the integrity of the river bank.

Rollingstone Bridge

Client: Townsville City Council

The Rollingstone Creek Timber Bridge Replacement

Ross Island Dredging

Client: Serco Sedexo Defence Services

This project was completed at the 10FSB amphibious landing craft facility at Ross Island Townsville. CivilPlus were engaged to dredge 3500m3 of spoil from the marina basin to ensure the ADF site...

Ross Island Dredging

Client: Aurecon

Dredging of Ross Island for Department of Defence
The pontoons at 10FSB Townsville required the isolation and disconnection of all services prior to extraction from the marina berth. The pontoons were removed using a mobile gantry crane and loaded...
CivilPlus constructions won the $1.2 million contract to design, build and install two new floating walkways just north of the city to Saunders and Bushland Beach boat ramps. The upgrade has...

Silver Creek Bridge Piles

Client: Mackay Regional Council

The nature of works requires Compliance with Quality, WHS and Environmental legislation Supply and install steel liners Excavate piles Supply and install reinforced cages and concrete...

Speed Creek Bridge Works

Client: GHD / ADF

This Contract was at Speed Creek located within the Australian Defence Force TFTA site. Previous construction had not been adequate to stop undermining of the existing abutment and CivilPlus were...

Storm Water TBRP Stage 2

Client: Townsville City Council

Constructions of TRBP Stage 2 Storm Water. Installation of 1500RCP & 1800RCP with associated stormwater manholes, Kerb inlet pits and Outlet structure in tidal water.

Stuart Drive Water Main

Client: Townsville Water

Supply and installation 2km DN630PE, DN500DICL, DN450DICL and DN375DICL water main. Also included installation DN750RCP enveloper pipe with some of this being bored and jacked under Stuart Drive /...

TCC Washdown Facilities

Client: Townsville City Council

CivilPlus were engaged to construct a Wash down Facility at the TCC Bamford Lane depot to facilitate the wash down of the garbage trucks after each shift. This included the installation of a...
The aim of this project is to construct a new booster pump station to pump water to Kulburn reservoir and northern areas of Townsville. The works involves a Pump House building construction to...
The aim of this project is to upgrade the Horseshoe Bay water distribution main by installing a new DN200-DN250 Main up to the distribution tank at Horsehoe bay. This works consists of the...
Road construction works including site hardening, installation of drainage and erosion prevention works, roads and tracks inc any required use of quarry resources, mechanical stabilisation of...

TFTA Civil Road Works

Client: SSDS

The Project Consisted of Road Maintenance Grading and formation, Concrete creek crossing consisting of Stabilised Gravel Base, Concrete Causeway and stabilised approaches as well as Stabilised...
The aim of this project is to restore the Picnic Bay jetty to a condition to allow the public access to the jetty. This involves timber girder strengthening and replacement, concrete & timber...

Tondara Road Upgrade

Client: Evolution Mining

Carry out works to upgrade earthworks and roads at the Evolution Mine Site
Road Construction works including site hardening, installation of drainage and erosion prevention works maintenance of access roads & tracks inc any required use of quarry resources, mechanical...
CivilPlus were required to complete multiple sheet pile driven retaining walls for the Townsville Hospital elevator shafts for the expansion of the emergency facility at Douglas. This was a design...