This project was for the provision of Inlet structure access reinstatement for Collinsville Low Lift Pump Station. Previously there was no access to the intake structure and as a result maintenance...
This project was for the provision of Inlet structure access reinstatement for Collinsville Low Lift Pump Station. Previously there was no access to the intake structure and as a result maintenance...
Installation of new Effluent line across the Haughton River Rail Bridge, the installation included 40 new trusses and 440m of pipe. The project encountered delays due to the work approvals from QR,...
This Contract was located at James Cook University (JCU) in Townsville. CivilPlus were engaged to complete all civil constructions to allow the installation of a prefabricated 8mtr long pedestrian...
Installation of Concrete valve pit and associated pipework to provide flow metering for the Kalynda Chase bulk water supply. The works included a concrete valve pit 5.5m x 2.5m x 1.8m deep which...
CivilPlus were engaged to install the various pipelines required for the new Water Treatment Facility which would upgrade supply to Townsville and surrounding suburbs. The 30 pipelines consisted of...
This Contract was located at Koombooloomba approx 37klm from the township of Ravenshoe in Far North Queensland. Stanwell Limited Corporation required the existing timber deck to be replaced due to...
Construction consisted of remediation works to improve the busy main entrance of Lavarack barracks, Townsville. Known as Melton Black Drive. The works include - the excavation of asphalt surface...
CivilPlus were engaged by Serco Sodexo to complete remediation works at the High Range Training Facility. The works included construction of a 40m causeway and gabion retaining wall. Also...
This project required the replacement of damaged landward mooring piles, delivery and installation new timber dolphins, remove selected fender piles from inshore services, dispose adjacent inshore...
CivilPlus were engaged to design and construct a new obstruction tower located at Mount Cook on Magnetic Island. The existing tower had been overgrown by the tree canopy and was not able to be...
Installation of 1.5km of 550mm HDPE Pipe installed through the Mangroves, Mudflat and Reef flat. This involved working in sensitive marine areas to remove mangroves and treat ASS soils to minimise...
Cape Hotham projects into the Van Dieman Gulf, approximately 80 km (direct line) NE of Darwin. The structure is a steel lattice tower capped by the lantern room with a copper roof. Surfaces to be...
Construct 1.2km of DN1300 pipeline to replace the existing redundant pipeline along Mann Road, Home Hill.
1.2km of DN1300 GRP Pipeline
29m of microtunneling under kirknie Road and Tram Line...
The aim of this project was to carry out civil repair to the deteriorated sealed munitions compound pavement at Mt Stuart Training Area to enable better access to training facilities in order to...
CivilPlus were engaged by Serco Sedexo for the refurbishment of the Range Target Mounds at MSTA. The works included placing bitum on re-compacted scour, placement of geoweb with fibre glass pins...
NQ1648 MIRR/3122 The Upgrade of the Mt Isa ARES depot pavement and hardstand areas. This included upgrading of the parade and parking bays for the depot, along with concrete light vehicle hardstand.
Pipe Welding Subcontract
CivilPlus (previously CivMEC) Constructions were initially subcontracted to complete the internal and external welds of the 800mm diameter MSCL Pipeline. However our scope...
Completion of 14 Lot sub division including sealed access roads, water reticulation, bulk earthworks and drainage works. Worked with client to overcome problems which arose with clashes of...
CivilPlus was awarded the project from Townsville City Council for the rehabilitation of the vehicle and pedestrian bridge on Mount Stuart Road. The bridge is situated at the intersection of Mount...
The aim of this project is for maintainance on the Infrustructure at the defence training facility, in particular the roadway to the MTR upgraded a gravel road to a Bitumen sealed road. This...
CivilPlus completed the concrete pathway from Base Backpackers Resort to Yates Street for the Townsville City Council to improve access for island users. This project required community and...
The aim of the project was to provide temporary new facilities for the relocation of two nearby health companies. CivilPlus completed the pre-works and services, including drainage, bulk earthworks...
This Contract was located at Ollera Creek near the foot of the Paluma Range. The objective was to remediate the existing pipeline surface where rusting had occurred due to river debris impacting...
The aim of this project is to replace the damaged existing jetty with a new Steel Substructure with timber decking jetty on Orpheus Island. This included driven steel pile with steel headstocks and...
Project Description / Overview:Installation of removal and replacement of sections of pipes ranging in size from 445mm to 660mm in areas with extremely difficult access and in the World Tropics...
The concrete dam inlet tower and outlet pipe has become dilapidated over time requiring remediation to stop current corrosion and further deterioration and water ingress.
CivilPlus has just completed works at the Picnic Bay Landfill. This project required the capping of the closed solid waste landfill at the Picnic Bay site. The purpose of these works was to create...
POTL required a new RCBC (2.4 x 1.5mtrs) drainage system to reduce flood zones and to allow future expansion sites to be available & suitable for construction as approved.
The Proserpine Boat ramp required upgrading to provide safer and increased access by the community. The major items included in the Works are: Design of the floating walkway (including construction...
Installation of Civil Works for Palm Island Jetty & Barge Ramp Upgrade, which included placement of select fill, placement of armour rock, Precast & Cast insitu items for the Barge ramp...
Installation of repairs to QN fuel oil line at approximately 37 locations between the Port of Townsville and QN Yabulu Refinery. This scope of works included the excavation of the sections of pipe,...
Installation of reinforced concrete footing to support the oil furnace stack, the footing was supported by driven precast piles. The works including two small stormwater pits, nib walls and small...
Project Description / Overview:CivilPlus are currently contracted by Queensland Nickel to reconstruct the main intersection at the Yabulu refinery due to a failing pavement causing continuous...
Civilplus have been contracted to install 240m of 1500 span concrete inverted culvert to the perimeter of the main warehouse facility at Queensland Nickel. This is to provide drainage to the...
The works consist of removal of existing guard rail and concrete slab, location of existing HV services, preparation of foundations and construction of 3 pad footings to accommodate two new plate...
Queensland Rail engaged CivilPlus Constructions to address a failed rail track drainage system under the road at Brandon, which had caused subsidence and cracking in the road surface. If left...
CivilPlus were engaged by Serco Sodexo to design and construct a concrete car park at the Townsville RAAF Base for Air Services Australia. These works included geofabric placement over uneven...
Demolition at three fuel hydrant locations, Concrete slab (nil reinforcing) 1.5m wide x 10m long x 0.4 - 0.5m deep, Including concrete at hydrant and high point surrounds, Low point drains...
CivilPlus were engaged to construct a 180,000L Spelceptor tank at the RAAF Base fuel farm, this included precast items for the fire trap and anchor blocks. The 4m deep excavation was sheet piled to...
This Contract was located on the Townsville RAAF Base between Hangar 75 & the quadron 38 area. The pavement required repairs and the project involved the design & re-construction of the...
Carpentaria Gold have engaged C+ Services to construct a sediment dam on the Ravenswood Mine Site. The purpose of the works is to capture runoff from the adjacent waste rock dumps prior to runoff...
Civilplus worked in conjunction with the Richmond Shire Council to complete Flood damage repairs on the Department of Main Roads owned Flinders Highway. This works consisted of catergorising...
The works consisted of demolishing and removal of existing bridge and abutments, and fabrication and installation of a steel painted bridge with connecting concrete pathways as per A.S and council...
Due to severe scouring of the river bank, Townsville City Council contracted CivilPlus to complete a designed gabion structure to restore the integrity of the river bank.
This project was completed at the 10FSB amphibious landing craft facility at Ross Island Townsville. CivilPlus were engaged to dredge 3500m3 of spoil from the marina basin to ensure the ADF site...
The pontoons at 10FSB Townsville required the isolation and disconnection of all services prior to extraction from the marina berth. The pontoons were removed using a mobile gantry crane and loaded...
CivilPlus constructions won the $1.2 million contract to design, build and install two new floating walkways just north of the city to Saunders and Bushland Beach boat ramps. The upgrade has...